This was a townhome in Anoka, fall 2026. I started on October 1 and the main level, about 1,600 square feet, took 5 days. Walls throughout: both bedrooms, the bathrooms, the kitchen and dining area, the living room, the foyer and hallways, the laundry room, the walk-in closet, and the sunroom. Ceilings in both bedrooms and both bathrooms, including the vaulted bedroom ceilings.
Most of it went to Sherwin-Williams Lightweight Beige (SW 6092). The primary bedroom went a deep green, Homegrown Sage. The second bedroom was a pale mint before. The wood windows stayed wood, and the green makes them read a little darker.
The job grew a bit once I was in it. The primary bathroom was added to the scope, and so were 16 drywall patches. The homeowner supplied the paint on this one.